L1 Task Force Sprint #2 Status Update

L1 Task Force
2 min readFeb 4, 2023

--

The following summary provides a status update for activities for the L1 Task Force from January 20th to February 3rd, 2023.

Q1 Roadmap and Release Milestones

Currently, the L1 Task Force is on-schedule for reaching the milestone target dates listed below.

Q1 key releases include: Classic v1.0.5 Hotfix (Completed, Go-live on February 14th), Classic v1.0.6 (Binance Whitelist/Oracle Feeder and Burntax Split), Cosmos SDK Upgrade to v0.45.11, Tendermint upgrade to v0.34.24, and Classic release v2.0.4

Current Status

  • All items are currently on schedule and within budget.
  • Notional has been paid for the month of January 2023, fully concluding our business relationship with them.

Current Issues/Risks

  • Risk identified and communicated on Wednesday, Feb 1st via @luncburnarmy Twitter page. The team hopes to close this risk as soon as possible and mark it as resolved.

Sprint #2 Jan 20th to Feb 3rd
This sprint was very productive, with classic release v1.0.5 deployed to validators and central exchanges. Release v1.0.6 (dependent on governance) will be released in mid-February and go live prior to March 1st.

Ready to Start, In progress, and In Review will move into Sprint #3

The L1 Sprint #2 project board can be viewed in real-time at GitHub. The L1 Sprint #3 Project Board will be updated this upcoming Monday, following the sprint planning session.

Next sprint: February 6th to February 17th

Questions or Comments?

If you have any questions or comments with respect to how the development team is progressing, what may be coming up next, or have any other general questions — please do not hesitate to reach out.

--

--