SEW Infrastructure Limited had been awarded the work of cement concrete lining of Mahanadi Reservoir Project (MRP) Canals when I was their only consultant. This work was to be executed in a particular reach of 20 km.length within a fixed period of 24 months only
This being a very small project but with our very fast working with cement concrete paver, we could finish the whole work six months ahead of the schedule time of completion.