Project update October 4

We have made progress with resurfacing the bridge and concrete repairs have been made in the galleries. We are now waiting for the design of the temporary supports to be signed off. The supports have to be approved, and independently checked before being submitted to the Highways Authority for approval. This is safety critical.

--

--