Moses Lake Development Site
An ongoing, inside look at our Moses Lake facility
Dec 9th
POD 4Hundreds and hundreds of feet of massive cables are being laid out to feed the powerPOD 5 completing external electrical workPODs 6,7,8 — all fans installedPODs 6,7,8 transformers with HV switchgear installedWiring for electrical panels being pulledPODs 6,7,8 internal cable trays and wiring for PDUs being laid outPOD 3 (left) and 4 (right)Dec 5th
Placing transformers for PODs 6,7,8 to get wiredPOD 6 internal electrical work is being doneNetwork and miner installation is being doneFans installed in 6 & 7 — almost done with 8Switchgear panels getting prepped for installationHigh voltage wire reels