The Neglect of George Wythe High School and Woodville Elementary School: A Timeline

La Negligencia de George Wyth High School y Woodville Elementary School: Una Cronología Recopilada por Jeannie Bowker

Homeroom
HomeroomVa
6 min readJul 30, 2021

--

Compiled by Jeannie Bowker

2002 — Richmond Public Schools (RPS) Facility Master Plan calls for major renovation of George Wythe High School (GWHS) and a new Woodville Elementary School (WES) (Source)

El plan maestro de instalaciones de las escuelas públicas de la ciudad de Richmond (RPS) exige grandes renovaciones para George Wyth High School (GWHS) y una nueva Woodville Elementary School (WES). (Fuente)

2007 — RPS Facilities Report again calls for new WES and major renovation of GWHS along with John Marshall & Armstrong High Schools (Source)

El informe de instalaciones de RPS otra vez exige una nueva WES y grandes renovaciones para GWHS junto con John Marshall & Armstrong High Schools. (Fuente)

June 2007 — Capital Improvement Program Budget for FY 2008–2012 adopted with a new WES planning phase scheduled for FY 2012 (Source)

El presupuesto para mejoras de capital de programas para los años fiscales 2008–2012 es adoptado con una fase de planificación para una nueva WES programada para el año fiscal 2012. (Fuente)

2010–2014 — Construction of Huguenot High School, Martin Luther King, Jr., Middle School, and Oak Grove & Broad Rock Elementary Schools overseen by the City (Source)

La construcción de Huguenot High School, Martin Luther King, Jr., Middle School, Oak Grove Elementary School y Broad Rock Elementary School, supervisadas por la ciudad de Richmond. (Fuente)

2014–2015 — RPS convenes a facilities task force to address dilapidated school buildings. Mayor Dwight Jones calls the push to fix infrastructure a “distraction.” (Source 1) (Source 2) (Source 3)

RPS convoca una fuerza especial de instalaciones para abordar los ruinosos edificios escolares. El alcalde Dwight Jones llama el esfuerzo para arreglar la infraestructura una “distracción.” (Fuente 1) (Fuente 2) (Fuente 3)

Nov 2017 — Voters approve a charter measure requiring the Mayor to plan to fully fund the modernization of every city school, going into effect on July 1, 2018 (Source)

Los votantes aprueban una medida del acta constitutiva requiriendo que el alcalde provea los fondos completos para la modernización de todas las escuelas de la ciudad, estando vigente el 1 de julio de 2018 (Fuente)

Dec 2017 — RPS School Board moves to address failing school infrastructure with a $224.8 million plan to build new schools, including a new GWHS and WES, and complete major renovations at Fairfield & Francis Elementary Schools. This is the 5th time since 2002 that the School Board has adopted a facilities plan that depends on city funding. (Source 1) (Source 2) (Source 3)

El comité escolar de RPS se prepara para abordar la infraestructura deteriorada escolar con un plan de $224.8 millones para construir nuevas escuelas, incluyendo GWHS y WES, y renovaciones completas para Fairfield & Francis Elementary Schools. Esta es la quinta vez desde 2002 que el comité escolar ha adoptado un plan de instalaciones que depende de fondos de la ciudad. (Fuente 1) (Fuente 2) (Fuente 3)

Feb 2018 — City Council votes 7–2 to approve the meals tax to fund RPS facilities (Source)

El consejo municipal vota 7–2 para aprobar el impuesto en comida consumida en restaurantes para financiar las instalaciones de RPS (Fuente)

Apr 2018 — Superintendent Kamras presents an updated facilities plan that does not include construction of a new WES and calls for GWHS to be completed on August 15, 2021 following a May 1, 2018 request for bids on construction (RFP). Kamras recommends collaborating with the City on building new schools on a Joint Construction Team (JCT) (Source 1) (Source 2)

El superintendente escolar Kamras presenta un plan de instalaciones actualizado que no incluye la construcción de una nueva WES y que pide que la construcción de GWHS esté terminada el 15 de agosto de 2021 después de expedir una solicitud de propuestas el 1 de mayo de 2018. Kamras recomienda colaborando con la ciudad de Richmond en un equipo de construcción colectivo (JCT).(Fuente 1) (Fuente 2)

June 2018 — JCT meets and discusses draft construction schedules for 3 new schools (Henry L. Marsh, III & Cardinal Elementary Schools and River City Middle School). There is no mention of a new GWHS. City says it will provide $100/110 million in funding instead of the full $224.8 million. (Source 1) (Source 2)

JCT se junta y discute planes de construcción para 3 nuevas escuelas (Henry L. Marsh, III Elementary School, Cardinal Elementary School y River City Middle School). No mencionan a GWHS. La ciudad de Richmond dice que preverá $100/110 millones de financiación en vez del completo $224.8 millones. (Fuente 1) (Fuente 2)

Dec 2018 — Kamras calls for construction of a new GWHS to start in 2021 and be completed in 2023, with funding TBD, in the Dreams4RPS Strategic Plan. There is no mention of WES. (Source)

Kamras pide que la construcción para una nueva GWHS comience en 2021 y termine en 2023, con fondos por determinar, en el plan estratégico “Dreams4RPS”. El plan no menciona a WES. (Fuente)

Feb 2019 — Construction starts on the 3 new schools (Source)

Se inicia la construcción de las 3 escuelas nuevas. (Fuente)

April 2019 — Cost for the 3 new schools is $140 million, $40 million over budget ​​(Source)

El precio de las 3 escuelas nuevas es $140 millones, $40 millones por encima del presupuesto. (Fuente)

Aug 2020 — Construction on 3 schools is complete, but the schools did not have certificates of occupancy and have ongoing punch list issues (Source)

La construcción de las tres escuelas ha terminado, pero las escuelas no tienen los certificados de ocupación y tienen una lista de pendientes en curso. (Fuente)

Oct 2020 — Mayor Stoney announces construction of new GWHS a few weeks before city elections in November (Source)

El alcalde Stoney anuncia la construcción de una nueva GWHS unas semanas antes de las elecciones de la ciudad de Richmond en noviembre. (Fuente)

Feb 2021 — Stoney states funding for GWHS will not be available until 2023 or 2024. Construction cannot begin until money is available. It takes at least 18 months to build a school, putting potential completion in 2025 or later. (Source)

Stoney declara que los fondos para GWHS no estarán disponibles hasta 2023 o 2024. La construcción no puede empezar hasta que los fondos estén disponibles. La construcción tardaría por lo menos 18 meses y terminaría en 2025 o potencialmente más tarde. (Fuente)

Apr 2021 — School Board passes “Schools Build Schools” Resolution to reclaim its right under Virginia law to build schools, transferring the power to build schools from the city to the school board (Source)

El comité escolar aprueba la resolución “Schools Build Schools” para reclamar su derecho según la ley de Virginia para construir escuelas, transfiriendo el poder de construir escuelas de la ciudad de Richmond al comité escolar. (Fuente)

June 2021 — City issues RFP for GWHS despite the School Board’s resolutions, contending that the City can build GWHS faster than RPS despite the City having repeatedly failed to fund a new GWHS for the better part of 3 years and still not securing funding (Source)

La ciudad de Richmond expide una solicitud de propuestas para GWHS a pesar de las resoluciones del comité escolar, sosteniendo que la ciudad de Richmond puede construir GWHS más rápido que RPS a pesar de que la ciudad de Richmond ha repetidamente fallado a proveer los fondos para una nueva GWHS por casi 3 años. (Fuente)

July 2021 — School Board approves a proposal calling for RPS to issue a RFP for GWHS on August 21, 2021 and for WES on October 31, 2021 (Source)

El comité escolar aprueba una propuesta pidiendo que RPS expida una solicitud de propuestas para GWHS el 21 de agosto de 2021 y una para WES el 31 de octubre de 2021. (Fuente)

Jeannie Bowker is a parent of 3 RPS students and lives in the 3rd District. She ran all over Richmond as a member of track and cross country teams in high school and college. Jeannie has an undergraduate degree from VCU, a graduate degree in Nationalism & Ethnicity (seriously), and a law degree from Northeastern University School of Law, where she focused on research and refugee & immigration law. These days, Jeannie hangs with her 3 kids, works as a due diligence analyst, and bakes when things get chaotic, which is often.

--

--