10 Powerful Strategies To Break Down Product Backlog Items in Scrum (with cheatsheet)

Christiaan Verwijs
The Liberators
Published in
19 min readApr 1, 2017

--

Teams that have mastered Scrum know that the key to success lies in a just-in-time, increasingly refined, breakdown of work on the Product Backlog. They prefer Sprint Backlogs with many small (functional) items instead of just a few large ones. Smaller items improve flow and reduce the risk of failing the sprint. In this article, I explain why the breakdown of work is important, and why it should be done across functional — instead of technical — boundaries. I also offer 10 useful strategies that experienced Scrum Teams use to break down work. Download the cheatsheet

We also recorded a podcast episode about this blog post on “The Liberators Network”. Listen to it here.

Why and when to break down items

Software development is inherently unpredictable. Some Product Backlog Items (PBI’s) on a backlog will require more effort than expected, while other items will require less. So if the work for a sprint contains only a few large items, the impact of underestimating the work on even a single item will have a profound impact on the sprint. And since larger items tend to be harder to estimate and understand, the potential for a failed sprint increases further.

Experienced Scrum Teams spend time and effort to break down large PBI’s into smaller stories. Although they sometimes do this during the planning of a new Sprint, they have learned that this process of ‘refinement’ should be continuous in order to make sprints — and particularly sprint planning — run smoother. So when a sprint is underway, the team also spends time breaking down PBI’s for the next sprint, and maybe even for the sprint after that. But this is done in a ‘just-in-time’-manner, so the team spends increasingly less time on sprints that are increasingly further down the road.

This process of breaking down work improves shared understanding and facilitates the Product Owner in the prioritization of work. But it isn’t easy to do well, and takes practice to do it ‘on the fly’. Thankfully, members of the Agile community — like Dean Leffingwell, Richard Lawrence and Mike Cohn — have devised a number of useful strategies for breaking down work into smaller bits.

Why a vertical break-down is superior to a horizontal one

Broadly speaking, there are two approaches for breaking up large PBI’s. The first approach is called ‘horizontal break-down and involves breaking down stories by the kind of work that needs to be done, or the layers or components that are involved. So, work that has to be done for the UI, the database, some components, a front-end, and testing are split up into technical items on the Backlog. This doesn’t work well in Scrum for several reasons:

  • Individual items do not result in working, demonstrable, software: Suppose that a team works on an order process for a webshop in a sprint. If they would split up the PBI horizontally, they would end up with work for design, database, front-end, and testing. Although the items are certainly smaller, they don’t deliver working software on their own. After all, a new bit of functionality can’t go live when only the UI is finished, or when only the database was modified. It is also a bad idea to go live without sufficient testing. So, individual items do not result in working, demonstrable, software, and — by extension — business value. Only the combination of all the work generates business value. But only if all the tasks are completed. And this is often a problem, as the next bullet explains;
  • Increases bottlenecks, instead of reducing them: Horizontal break-down is often accompanied by ‘silo thinking’. Every member is taken from one of the silos required for software development. The ‘design person’ will take care of the design, the ‘database person’ will set up the database, the ‘developer’ writes the code and the ‘tester’ does the testing. If team members are not interchangeable (which is often the case when using this approach) there is a good chance of bottlenecks. If the ‘design person’ can’t get his work done on time, this will impact the tasks that follow the design. Because team members can’t help each other out, every delay, problem, or interruption will impact the entire sprint;
  • Horizontal slices can’t be prioritized: How can a Product Owner prioritize a backlog if it consists of horizontal slices? Because none of the items deliver business value or working software on their own, a Product Owner will be unable to prioritize work. There is also a good chance that the slices will be fairly technical, which creates distance and misunderstanding between the Product Owner and the team;

Although a horizontal break-down of PBI’s will result in smaller items, it severely limits the ability of a team to deliver working software, work around bottlenecks and prioritize work. It, therefore, increases the risk of failing the sprint. A bad idea.

In Scrum, a vertical break-down is more useful, in which PBI’s are broken down into smaller PBI’s (instead of technical tasks). If PBI’s are broken down vertically, they are broken down in such a way that smaller items still result in working, demonstrable, software. Functionality will not be split across technical layers or tasks but across functional layers. So, if the PBI is ‘As a customer, I can pay for my order, so I can get my products’, it can be broken down into smaller PBI’s like ‘As a customer, I can pay by wire transfer, so I can get my products’ or ‘As a customer, I can pay with a credit card, so I can get my products’.

A metaphor will further clarify the difference. Imagine slicing a cake with layers of cream, fruit, and cake. If you would cut a cake horizontally, every guest would only get a slice of cake, cream, or fruit. I’m sure that your guests would’ve expected something else. Getting just a single layer of the cake does not allow them to sample the entire cake. A friendlier approach is to slice the cake up in vertical slices, each with a bit of cake, cream, and fruit:

There are many strategies available for breaking down large PBI’s. I have collected ten of the most useful ones. And you can even download a handy cheat sheet at the bottom of this page. As you will see, these strategies not only help in breaking down PBI’s, they also help in deciding what is important and what is not. This way, the Product Owner can more easily prioritize the work and make more informed decisions on what the Scrum Team should spend time on.

Strategy 1: Breaking down by workflow steps

If PBI’s involve a workflow of some kind, the item can usually be broken up into individual steps. Take a PBI for an order process of a regular webshop:

As customer I can pay for the goods in my shopping basket, so that I receive my products at home

Given a fairly standard order procedure, we could identify the following steps:

  • As customer I can log-in with my account, so I don’t have to re-enter my personal — information every time;
  • As customer I can review and confirm my order, so I can correct mistakes before I pay;
  • As customer I can pay for my order with a wire transfer, so that I can confirm my order;
  • As customer I can pay for my order with credit card, so that I can confirm my order;
  • As customer I receive a confirmation email with my order, so I have proof of my purchase;

By breaking down a large PBI like this, we have improved our understanding. It will also be easier for a Product Owner to prioritize the work. Some steps in the workflow may not be important right now, and can be moved to future sprints. Perhaps the order confirmation email can be done by hand for the time being, or customers can only pay with credit card for now. It might also be ok to require customers to (temporarily) re-enter their personal information for every order. This will certainly limit the functionality of the webshop, but it does allow a Scrum Team to review (and maybe even deploy) the completed functionality at the end of the sprint, test it and use the feedback to make necessary changes.

Strategy 2: Breaking down by business rules

PBI’s often involve a number of explicit or implicit business rules. Take this PB, again for the order process of a regular webshop:

As customer I can purchase the goods in my shopping basket, so that I can receive my products at home

Given a fairly standard order procedure, we could identify the following ‘business rules’:

  • As shop owner I can decline orders below 10 dollars, because they aren’t profitable;
  • As shop owner I can decline customers from outside the US, because the shipping expenses make these orders unprofitable;
  • As shop owner I can reserve ordered products from stock for 48 hours, so other customers see a realistic stock;
  • As shop owner I can automatically cancel orders for which I have not received payment within 48 hours, so I can sell them again to other customers;

Business rules are often implicit, so it will take some skill and analytical prowess to unearth them. It may help to employ another strategy (described below, #7); how is the functionality going to be tested? Often, test cases imply important business rules. Once the business rules have been identified, they will again have improved our understanding. The product owner may decide that some business rules are not important for now or can be implemented in a simplified form. Perhaps it’s ok for now to manually return unpaid products to stock when a payment has not been received within 48 hours, or orders can be canceled manually. Even more pragmatically, a message on the site explaining that ‘orders are not shipped outside the US’ or that ‘the minimum order price has to be at least 10 dollars’ may be sufficient for now. It will save time and money required to enforce this business rule.

Strategy 3: Breaking down by happy / unhappy flow

Functionality often involves a happy flow and one or more unhappy flows. The happy flow describes how functionality behaves when everything goes well. If there are deviations, exceptions or other problems, unhappy flows are invoked. Take this PBI for logging in to a secure website:

As customer I can log in with my account, so that I can access secured pages

If we consider a regular login procedure, we can identify a happy flow and several potential unhappy flows:

  • As a user I can log in with my account so that I can access secure pages (happy);
  • As a user I am able to reset my password when my login fails, so I can try to log in again (unhappy);
  • As a user, I am given the option to register a new account if my login is not known, so I can gain access to secure pages (unhappy);
  • As owner of the site, I can block users that log in incorrectly three times in a row, so I can protect the site against hackers (unhappy);

Unhappy flows describe exceptions. By identifying the various flows, we more clearly understand the required functionality. A Product Owner can more easily decide what is important right now. Perhaps blocking users after three failures is not important right now, because there are only a handful of users in the first version anyways. Or perhaps a reset of passwords can be done by sending an email to a customer care employee for the time being. Again, by splitting up functionality we can more accurately ask questions about the business value, and make decisions accordingly.

You may not need to have iPad-support right away

Strategy 4: Breaking down by input options / platform

Most web applications have to support various input options and/or platforms, like desktops, tablets, mobile phones or touchscreens. It may be beneficial to break down large items by their input options. Take a digital Scrum Board for a team:

As team member I can view the Scrum Board, so I know how we’re doing as a team

We can identify the following input options:

  • As team member I can view the Scrum Board on my desktop, so I know the status of the sprint;
  • As team member I can view the Scrum Board on my mobile phone, so I know the status of the sprint;
  • As team member I can view the Scrum Board on a touchscreen, so I know the status of the sprint;
  • As team member I can view the Scrum Board on a print-out, so I know the status of the sprint;

By breaking down large items this way, the Product Owner can more easily prioritize which input options or platforms are more important. A desktop-version is likely to be sufficient for now, while a mobile version can be pushed to a future sprint. Or perhaps the print-out can be implemented with a simple PDF capture for the time being, without having to create a version specifically suited for print.

Strategy 5: Breaking down by data types or parameters

Some PBI’s can be split based on the datatypes they return or the parameters they are supposed to handle. Take, for example, a search function for a webshop:

As customer I can search for products so I can view and order them

There are many ways to search for a product. All these potential parameters can be considered and broken up into smaller PBI’s:

  • As customer I can search for a product by its product number, so I can quickly find a product that I already know;
  • As customer I can search for products in a price range, so that the search results are more relevant;
  • As customer I can search for products by their color, so that the search results are more relevant;
  • As customer I can search for products in a product group, so that the search results are more relevant;

By breaking down the search functionality in this manner, we more clearly understand what kind of search parameters will be used. This allows a Product Owner to make decisions about priority. Maybe paging is not yet relevant because of the small number of products. It might become relevant when the number of products grows. Or maybe some of the search functionality can be implemented in a simplified manner for now. Another example of this strategy is when breaking up functionality involving management information based on the returning data types. Some of the information can be presented visually in charts or graphs (data types), but can also be displayed in a tabular format (datatype) for now. Perhaps the Product Owner is ok with exporting the data to Excel and manually creating all the graphs and charts there for the time being.

Strategy 6: Breaking down by operations

PBI’s often involves a number of default operations, such as Create, Read, Update or Deleted (commonly abbreviated as CRUD). CRUD operations are very prevalent when functionality involves the management of entities, such as products, users or orders:

As shop owner I can manage products in my webshop, so I can update price and product information if it is changed

By identifying the individual operations required for this functionality, we can derive the following smaller bits of functionality:

  • As shop owner I can add new products, so customers can purchase them;
  • As shop owner I can update existing products, so I can adjust for changes in pricing or product information;
  • As shop owner I can delete products, so I can remove products that I no longer stock;
  • As shop owner I can hide products, so they cannot be sold for the time being;

When presented with this strategy, many teams wonder if the smaller items actually deliver business value. After all, what’s the point of only creating entities when you cannot update or delete them afterward? But perhaps the Product Owner has such a limited number of products, that editing or deleting can be done in the database directly. Sometimes, an operation can be easily implemented in a simplified form. Deleting a product can be done in two ways; you can completely drop the record and all associated records, or you can ‘soft delete’ a product. In that case, the product is still in the database, but it is marked as ‘deleted’. Sometimes one of these approaches is easier to implement and can be ‘good enough’ for now.

Strategy 7: Breaking down by test scenarios / test case

This strategy is useful when it is hard to break down large PBI’s based on functionality alone. In that case, it helps to ask how a piece of functionality is going to be tested. Which scenarios have to be checked in order to know if the functionality works? Take a task planning system:

As manager I can assign tasks to employees, so they can work on tasks

If we consider this functionality based on potential scenarios, we can break down the item into:

  • Test case 1: If an employee is already assigned, he or she cannot be assigned to another task;
  • Test case 2: If an employee has reported in sick, he or she should be visually marked;
  • Test case 3: If an employee has reported in sick, he or she cannot be assigned to a task;
  • Test case 4: If an employee is not yet assigned, they can be assigned to a task;
  • Test case 5: Employees can be assigned with a touchscreen monitor;

This strategy actually helps you apply the other strategies implicitly. By thinking about testing, you automatically end up with a number of business rules (#1, #2, #3, and #4), (un)happy flows (#1, #2, and #3), and even input options (#5). Sometimes, test scenarios can be very complicated because of the work involved to set up the tests and work through them. If a test scenario is not very common, to begin with, or does not present a high enough risk, a Product Owner can decide to skip the functionality for the time being and focus on test scenarios that deliver more value. In other cases, test scenarios can be simplified to cover the most urgent issues. Either way, relevant test scenarios can be easily translated into backlog items and added to the sprint or the backlog.

Strategy 8: Breaking down by roles

PBI’s often involves a number of roles (or groups) that perform parts of that functionality. Take a PBI to publish new articles to a public newspaper website:

As news organization we can publish new articles on our homepage, so customers have a reason to return periodically

By considering the various roles that are involved, we can break the functionality down into the following bits:

  • As customer, I can read a new article, so I can be informed of important events;
  • As journalist, I can write an article, so it can be read by our customers;
  • As an editor I can review the article before putting it on the site so that we can prevent typos;
  • As admin I can remove articles from the site so that we can pull offending articles;
  • As a customer, I can review and confirm my order, so I can correct mistakes before I pay;

By breaking down functionality into the roles that have to perform bits of that functionality, we more clearly understand what functionality is needed. Writing PBI’s is a great way to apply this strategy. It also helps the Product Owner to prioritize. Some roles may be less relevant at the moment and can be implemented later. Perhaps there is no need at the time for an editor. Or the editor can be called by a journalist to check the article manually.

Strategy 9: Breaking down by ‘optimize now’ vs ‘optimize later’

Often, PBI’s can be implemented in varying degrees of perfection and optimization of the functionality described. Take this PBI:

As visitor I can search for hotels in a neighborhood, so I can narrow my search

This item could be broken down in varying degrees of optimization:

  • As visitor I can search for hotels based within a radius from an address, so I can narrow down my search;
  • As visitor I can enter the zip code to auto-complete the address, so I don’t have to enter the entire address manually;
  • As visitor I can use my location (GPS) to search in the neighborhood, so I don’t have to enter the address manually;
  • As visitor I get the most-searched hotels in the neighborhood right away, while other hotels are loading in the background, so I more quickly get results;

Let me be clear on one thing: this strategy is not supposed to be used as an excuse to write ‘crappy code’ now and ‘better code’ in the future. Scrum Teams should always strive to deliver code that is maintainable, (automatically) tested and well-written. This strategy is concerned with functional optimization. In any case, a Product Owner can more easily prioritize these items. Perhaps it is sufficient for now to let visitors search by address (and a radius), while more complex functionality (auto-completion, GPS) is implemented in the future.

Strategy 10: Breaking down by browser compatibility

In a variation of strategy #4, this strategy breaks down work by the platforms that need to be supported. For web applications, these could be the different browser versions you need to support. Modern browsers tend to be more compliant to standards, and easier to develop for, while older browsers often require hacks and customizations to get everything to work properly. But you can also apply this strategy to embedded systems where you need to support many types of hardware with your software.

Lets apply the strategy to this large item:

As customer I can view product details, so I know if I want to buy it

By considering the browser versions, we can break down the work into smaller items:

  • As customer, I can view product details in a standards-compliant, modern browser, so I know if I want to buy it;
  • As customer, I can view product details in IE7, so I know if I want to buy it;
  • As customer, I can view product details in a text browser, so I know if I want to buy it;

Although it would certainly be preferable to deliver this functionality with full support for all browser versions, there are certain scenarios where this break-down is feasible. Perhaps the vast majority of the visitors use modern browsers, requiring less effort to support old browsers (other than a warning). Or maybe the application is run on an internal network where all users use Internet Explorer 7. Again, this allows the Product Owner to prioritize and helps to team to spend time and effort on the most important functionality first.

Other strategies

There are many other strategies that are helpful when breaking down large PBI’s:

  • Break down items based on identified acceptance criteria. This may seem very obvious, but it’s often the easiest and most natural way to break down a PBI. Mapping out acceptance criteria for a PBI requires similar strategies like the ones described in this post;
  • Break down items based on the parts that are hard to implement and the parts that are easier. It may be difficult to set up a piece of functionality in a heavily designed UI, but getting it to work with a simple UI may be easy and sufficient for now. Again, it’s all about being pragmatic and delivering business value;
  • Break down items based on external dependencies. Sometimes functionality is dependent on external factors, such as implementing a consumer for a remote webservice (e.g. for electronic payment or connecting to Twitter). This may be difficult, but may not have the highest priority. Or the dependencies can be mocked for the time being;
  • Break down items based on usability requirements. This includes functionality for paging through a list of records, making a website readable for blind people or people with colorblindness, or implementing breadcrumbs;
  • Break down items based on SEO requirements, such as setting up dedicated landing pages for specific keywords, setting up goals for Google Analytics, or setting up XML sitemaps;

When is a Product Backlog Item small enough?

There is no clear-cut rule on how small a PBI should ideally be. This greatly depends on the length of the sprints, the nature of the application, and the size and experience of the team. It often takes a Scrum Team several sprints to figure out the sweet spot.

My own experience is that teams should strive to add at least between 5 and 8 items to a one-week sprint (one per day). They don’t have to be of equal size, but they shouldn’t be too big on their own. This also gives a clear goal to the refinement process of upcoming work.

On potential concerns from the Scrum Team

There are some concerns that I often hear from Scrum Teams when they’re trying to break down PBI’s. The first is that teams are worried about the reduced business value of smaller items. Of course, smaller items will have reduced business value compared to the larger item. But the primary purpose of breaking down functionality is to reduce risk, increase flow and increase the amount of working functionality that can be reviewed at the end of every sprint. The alternative is to keep working with very large chunks of functionality, with all the aforementioned consequences and risks.

Another concern is that breaking down functionality results in more work. For a team, it’s often easier and faster to keep working on a piece of functionality until it’s completely done. Revisiting bits and pieces throughout the sprints feel wasteful. Although this may be true to some extent, there is good reason to still do this. In Scrum, we implement a process that is designed to continuously review and test our work and adjust according to the feedback we get. So, the functionality that you may have in mind now may be very different from what will actually be implemented when we use Scrum. Although it may be tempting to keep working on a piece of functionality, there is a good chance that you are wasting your time on functionality that will be changed further down the road (based on feedback from users, stakeholders, etc).

A final concern is that many teams do not immediately ‘get’ how to break down functionality. It is not uncommon to run into some resistance as a result. This is understandable; trying out new things is difficult because it makes people feel vulnerable. The best way to deal with this is to persist and gently coach the team by helping them break down their PBI’s.

Wrapping up

In this post, I have emphasized the importance of (continuously) breaking down large PBI’s into smaller ones. A sprint should preferably consist of many small items instead of only a few large ones. The fewer (and larger) the items in a sprint are, the larger the risk of failing the sprint. I have offered 10 well-known strategies used by experienced Scrum Teams that may be of use to your team. Good luck!

Download the cheatsheet or download a fully prepared string to refine a tough and very unclear item with stakeholders.

You can already support us with $1/month. Find out more on patreon.com/liberators

This post was originally published on blog.agilistic.nl (before 2013), and imported to Medium.