VNT Chain Labs
VNT Chain Labs
Published in
4 min readSep 27, 2018

--

VNT Weekly | VNT Chain Project Progress

VNT WEEKLY, September 23

This is the weekly report of VNT Chain in which you will find about the latest project updates, community news and development progress. It would be a great honor for us to share exciting news and build the ecology with you!

Project Updates

1.On September 18, the VNT Chain team visited one of the best universities in Asia, the National University of Singapore, who has a world-class computer school. The global technology ecology of VNT Chain begins here.

2. On September 19, Dr. Liu Zhenguang, chief scientist of VNT Chain, made a speech at the BlockChain Cocktail Party which was held in Singapore.

Liu Zhenguang, Ph.D in computer science of Zhejiang University, Postdocs in computer science of National University of Singapore, senior expert in blockchain and big data. Since 2011, he has published 15 papers in well-known conferences and journals in the areas of blockchain, data mining, and anomaly detection.

Community News

1. On September 19, in order to celebrate the launch of official website 2.0, and to express gratitude to the community, VNT Chain has sent out most sincere blessings with the “Crab” gifts! The first prize of the event was a box of hairy crabs + 2 kg of persimmons, the second prize was 5 kg of Shandong handmade big buns, the third prize was one VNT culture shirt, and the fourth prize was a small heart-shaped red envelope. A total of 2,288 VNT fans has participated in the “Mid-Autumn Festival” events by yesterday.

2. On September 23, the "Developer Platform Operation Guide II" has launched. Follow VNTer and start your developer journey now!

Developer platform URL: developers.vnt.link

Development Progress

Consensus Module

1. Consensus prototype development and joint adjustment — 100% Completed

2. Witness management function development – 85% Completed

3. Pre-research of Verifiable random function application pre-research in consensus prototype – 55%

4. Pre-research of the application of BFT in consensus prototype – 90% Completed

5. Integrated BFT plan design—75% Completed

Smart Contract Module

1. The contract language compiler is being perfecting. The development of branches and parameter verification is completed. – 40% Completed

2. Wasm compatibility test for smart contract programming –70% Completed

3. Research on smart contract formalization demonstration program—90% Completed

4. Optimize virtual machine exception handling mechanism—70% Completed

5. Support struct – 90% Completed

6. Improve Array – 70% Completed

7. Wavm supports the pre-research of uint256 – 40% Completed

8. Gas Design — 95% Completed

9. Design of WASM Virtual Machine Decoupling Scheme — 40% Completed

10. ABI generation tools support map and array — 50% Completed

11. Scheme design of contract secondary compilation — 35% Completed

P2P Module

1. Analyze event calls in the P2P layer. Being debugging – 40% Completed

2.Transaction transmission and block synchronization sub-protocol extension –85% Completed

3. Protocol modification based on libp2p data structure -- 75% Completed

4. Blacklist function development of network layer completed. Being debugging– 40% Completed

5. Intranet penetration function development of network layer — 30% Completed

6. Reader modification of protocol layer — 80% Completed

7. Support for protocols such as les, bzz, and shh — 30% Completed

8. Fix the bug of ending when the whole node starts up — 100% Completed

Cross Chain

1. Hash lock technology pre-research – 80% Completed

2. Hash lock scheme demo verification – 55% Completed

3. Notary public technology pre-research – 55% Completed

4. Side chain technology pre-research – 45% Completed

5. Combination of ring signature technology and notary public technology—45% Completed

Consortium Chain

1. The first round of functional testing of the Consortium Chain 1.1 version– 90% Completed

2. Fix defects such as restart of consortium chain V1.1 node — 100% Completed

3. Second round of functional testing of Developer platform — 85% Completed

4. Developer platform contract status display error and other defects fixed — 100%Completed

5. Stability test of developer platform — 35% Completed

6. Developer platform helped documentation bugs fixed –100% Completed

7. Research on the technical design of zero-knowledge proof — 60% Completed

--

--

VNT Chain Labs
VNT Chain Labs

VNT Chain targets to build a global distributed smart value network based on blockchain technology.