Mike Martin (& Dustin Guillemin)inIMM at TCNJ Senior Showcase 2018How’d it go?After many months of designing and constructing Turbo Pinball Ultra, we are finally finished. Although the lead-up to the show was super…May 2, 2018May 2, 2018
Mike Martin (& Dustin Guillemin)inIMM at TCNJ Senior Showcase 2018Home StretchNow that the showcase is rapidly approaching (even though it was was, but we are just now feeling the effects) we have entered 200%…Apr 17, 2018Apr 17, 2018
Mike Martin (& Dustin Guillemin)inIMM at TCNJ Senior Showcase 2018Revitalization. (Week 9)After past weeks of feeling that we were not accomplishing much this week has really been exciting. We accomplished a crazy amount this…Apr 10, 2018Apr 10, 2018
Mike Martin (& Dustin Guillemin)inIMM at TCNJ Senior Showcase 2018Week 8?Again as we continually move closer to the showcase, Dustin and I have been working day in and day out on completing this pinball machine…Apr 4, 2018Apr 4, 2018
Mike Martin (& Dustin Guillemin)inIMM at TCNJ Senior Showcase 2018Blood, sweat, and more blood(Week I don’t even know any more)As soon as spring break ended and both Dustin and I were back in Ewing, we hit the ground running ready to power through all of our work…Mar 27, 2018Mar 27, 2018
Mike Martin (& Dustin Guillemin)inIMM at TCNJ Senior Showcase 2018Week 6 Sprint (Final Steps)This week marked great progress for us as we continued towards making our machine a working analog pinball machine. Our play field is…Mar 7, 2018Mar 7, 2018
Mike Martin (& Dustin Guillemin)inIMM at TCNJ Senior Showcase 2018Broken Screws (Week 5)This week brought a lot of progress for us once again. The table is being put together and we plan finish construction of the table before…Feb 27, 2018Feb 27, 2018
Mike Martin (& Dustin Guillemin)inIMM at TCNJ Senior Showcase 2018Progress, Progress, Progress (Week 4)As we continue to work on our project, Dustin and I are continually seeing the potential of our project and look forward to creating a one…Feb 21, 2018Feb 21, 2018
Mike Martin (& Dustin Guillemin)inIMM at TCNJ Senior Showcase 2018Construction Week One (Week Three)This past week Dustin and I finally got to building our pinball machine. After gathering all of our materials we began initial measurements…Feb 13, 2018Feb 13, 2018
Mike Martin (& Dustin Guillemin)inIMM at TCNJ Senior Showcase 2018Pre-Construction Stage Week 2As we are continuing the pre-construction processes of our project, Dustin and I are finding that our plans are finally coming together…Feb 6, 2018Feb 6, 2018