Job Safety Analysis (JSA) is a simple mean of looking at the work task and considering what is the safest way to complete it.

Risk Assessment or JSA should be attached to the PtW

To Ensure That Potentially Conflicting Activities Are Not Performed

To İnform The Personnel About The Risk Evaluation During The TBT;

To Evaluate The Necessity Of A HEIC;

A Mitigation Measure Required İn The PTW

JSA is a way of becoming aware of the hazards involved in doing the job and taking action to prevent an injury.

Four basic stages in conducting a JSA are:

1.selecting the job to be analyzed;

2.breaking the job down into a sequence of steps;

3.identifying potential hazards;

4.determining preventive measures to overcome these hazards.

JSA filling example

Job Safety Analysis: Process shoud be divided by steps

1.Each step recorded in sequence

2. Each item is started with an action erect, install, place, use, hoist …etc…

3. Note what is done, not how it is done

Think the hazards and resulted risk

4-Evaluate and discuss each potential hazard, identifying the types of injuries that might occur.

5-Be sure to include those hazards that have a low occurrence rate or are unlikely to happen.

Physical Hazards (access, heights, electricity, noise, vibration)

Mechanisms of Injury (crush, strike against, slips, falls, overexertion)

Environmental Factors (lighting, heat, cold, pollution)

Personal Factors (competency, training, fitness, fatigue)

HOW TO PREPARE JOB SAFETY DOCUMENTS THIS VIDEO EXPLAIN WELL

Watch this video to learn how to prepared jsa documentation !
5S SAFETY HANDBOOK

My publication will take about 2 hour with reading totally. I have divided my publication into seven parts.

1st Part: Natural Requirement of a Work Permit. I will give a few basic definitions regarding to permit to work system.

2nd Part: Formal Ways Definition

3th Part: When is PTW required ?

4th Part: Permit to Work Family !

5th. Part: Simultaneous Operations (You are here)

6th Part: Examples of tasks requiring PTW (You are here this part)

6.1 Cold Work Permit

6.2 Hot Work Permit

6.3 The Radiography Work Permit

6.4 Confined Spaces Work Permit

6.5 Excavation Work Permit

6.6 Hazard Energies Isolation Certificate & Lock-Out- Tag-Out (LO-TO)

6.7 Grating/Handrail Removal & Open Hole Certificate for Construction

6.8 Working At Height Work Permit

7 th Part: I give you some facts and figures regarding to practicle example PTW and How we can organize Permit to Work Systems

7.1 Toolbox Talk (You are reading here)

7.2 RA/JSA and How to fill Job Safety Analysis (You are reading here)

7.3 Essentials Parts of PTW — First Part PTW Document

7.4 How to Monitor PTW System on field ? — First Part PTW Document Location

7.5 Essentials Parts of PTW — Second Part safety precautions

7.6 Essentials Parts of PTW Third part related to the issuing, starting and closure of the document

7.7 PTW REVALIDATION — Handover

7.8 Display Permit to Work Papers

7.9 Simple Flowchart Permit To Work Systems

7.10 Management Responsibilities &Site Responsibilities

--

--